Vineyards

Assistance to the regions of Bento Gonçalves, Carlos Barbosa, Farroupilha, Garibaldi and Lajeado, in addition to increasing the reliability of the system.

Sterlite Power

Project Story

The Vineyard Project has 114,4 km of transmission line to be built, the implementation of 2 new substations and the expansion of some substations in the region to be deployed in the state of Rio Grande do Sul. Power of 496 MVA.

Project Detail

Length: 115 km
Power: 230 kv

Timelines

Preliminary Environmental license

Installation Environmental license