São Francisco

Generation flow in the southern area of the Northeast region.

Sterlite Power

Project Story

The São Francisco Project has 521 km of transmission line to be built, the implementation of 1 new substation and the expansion of 4 other substations in the region of Sergipe e Bahia states.

This project is expected to generate 1545 direct / indirect jobs.

Project Detail

Length: 165 km     
Deadline: 60 months 
Estimate of direct jobs: 553
State: MG
TL 500 kV Governador
Valadares 6 - Mutum C2

Timelines

Preliminary Environmental license

Installation Environmental license